FINAL
INSPECTION & WARRANTY
Upon
substantial completion a final inspection is made to determine items
which need to be completed or corrected and a list prepared (normally
referred to as a punch list). The issuance of substantial completion
also marks the beginning of the warranty period. Generally, completion
of this list to the satisfaction of the client is required within
7 to 10 days (within reason) of issuance.
In general, warranty periods may vary slightly but irrigation systems,
lighting and hardscape elements are typically warranted for one
year, plantings with irrigation are typically warranted for one
year and plantings without irrigation are typically warranted for
90 days. In general, our plant material losses for one year do not
exceed 1% of sales. Extended warranties may be considered on an
as requested basis.